Installation & Training

Every system we ship can be installed and commissioned on your site by our own engineers. The procedure below is the standard sequence we follow: most single-machine installations are completed in one to two working days, and a complete laboratory line takes three to five.

  1. 1

    Site and utility preparation

    Before dispatch we send a site checklist covering floor loading, power supply, compressed air, drainage, ambient temperature and humidity. You confirm the figures and we confirm the machine layout drawing.

  2. 2

    Unpacking and positioning

    The machine is crated with shock indicators. Our engineer supervises unpacking, checks for transit damage and positions the unit on levelling feet or anchor bolts according to the layout drawing.

  3. 3

    Mechanical and utility connection

    Frames are levelled, fixtures and grips are mounted, and power, air and water lines are connected through the isolation devices specified in the manual.

  4. 4

    Software, calibration and verification

    Control software is installed and configured with your test methods and specimen templates. Load, displacement, pressure and temperature channels are verified against reference instruments and the readings are recorded in the acceptance protocol.

  5. 5

    Operator training

    Operators are trained on specimen preparation, method selection, daily checks and result interpretation, and each of them runs a complete test cycle unaided before the engineer leaves the site.

  6. 6

    Acceptance and handover

    A site acceptance test is performed against the agreed specification. The signed protocol, calibration certificates, spare parts list and electrical drawings are handed over for your quality system.

Site requirements

Item Requirement
Power supply AC 220 V or 380 V, 50/60 Hz, single or three phase according to model, with protective earth
Compressed air 0.6 to 0.8 MPa, dry and oil-free, for pneumatic grips and clamping devices
Cooling water 0.2 to 0.4 MPa, not above 25 °C, for hydraulic and high-temperature systems
Floor and space Level concrete floor, at least 3 x 2 m clear area, loading of 500 kg/m2 or more
Environment 10 to 35 °C, relative humidity up to 80 %, no corrosive gas and no strong vibration

Service around the installation

Remote commissioning

Where travel is restricted we commission over a video link: our engineer guides your technician through the same checklists and signs off the protocol remotely.

Spare parts and consumables

Wear parts, grips, seals, sensors and heating elements are kept in stock for at least ten years after delivery.

Preventive maintenance

Annual service visits cover calibration, mechanical inspection and software updates, and a service report is issued for your quality records.

Plan your installation

Send us the model list and your site address and we will confirm the schedule, the engineer assigned and the documents you need for customs and site access.

Request an installation schedule
Online Sales
P
Good day! Thank you for your visit!
We are a high-quality supplier and look forward to working with you!

You can leave your email or WhatsApp for further communication!

How to get product information?
How to view the factory online?
How to view samples online?
15:48:19